
Trinity Dome calls for #3 bars every 12" on center at the base of the dome tapering to 10" on center towards the top.

We also needed to add double #5 bars called for around each opening and across both saddles. The big bars are quite chore to work with.

Once the rebar was in place, the guys from Todd's Electric came and installed all the boxes and conduit needed on the exterior walls. They made quick work of it and wrapped up in a single day.
[ add comment ] ( 707 views ) | permalink
After priming the entire inside with a special "sticky paint", the dome was ready to foam.

Tom from Weather Guard Urethane in Yankton came over and sprayed the first few layers of foam. After spraying the first 1.5", he wrapped things up for the evening.

Between the two days of foaming, the rebar stickers were placed throughout the dome. The stickers are essentially wire tires attached to barbed plates that hold onto the foam. Once installed, Weatherguard came back and finished the foam for a total of 3".

Then Tom sprayed the footing with 3" from the outside. This completes the thermal break for the shallow footing and makes sure the radiant floor heating directs it's energy inward.
[ add comment ] ( 1111 views ) | permalink
Following inflation, the next step was to build and install the vinyl window bucks.

The bucks themselves were easy enough to cut and assemble. However, the process had to be repeated after the first installation attempt -- as they were just a bit too big all around to fit with full pressure on the airform.

It was especially hard to get the bucks level and plumb. The biggest issue was keeping them vertical under full pressure without breaking anything. The two largest bucks actually started to bend, and required adjustment and extra bracing.

This shot shows some of the straps and ground anchors used to keep the window areas as flat as possible vertically. Will did a nice job of working this out, and using a 4:1 pulley system to make his adjustments.

While monitoring the pressure in the airform, it was decided the many area leaves were a nuisance. Several times they built up on the fan and reduced the pressure, so an axtra cage was attached to keep it from plugging.
[ add comment ] ( 1201 views ) | permalink
The big day finally arrived. This was the moment the house went from a funny shaped concrete slab to a full size home in the round.

Will is attaching the inflator fan to the airform. We did this using metal strapping and self tapping screws. This was followed by attaching the airlock in a similar manner.

After a final check, the fan was finally plugged in and we inflated the airform. It went remarkably fast. For those of you with broadband, you can watch the video here .

The feeling inside is terrific. At nearly 13 feet high, the vaulted ceilings will make this little retirement house feel open and airy. Everyone is excited to move ahead.

Here's the view from the street. Now the "What is it?" questions have really picked up. You can't stop by without somebody asking about the house. And everyone has been pleased to hear the answer -- "It's a house." Many kudos to the residents of Vermillion for their open minds and desire to see something different being built!
[ add comment ] ( 1068 views ) | permalink
When the weather finally cleared, we were able to prepare for inflation in earnest. By the end of the week we were ready to go.

The first step was to dry out the lot a little and get the area workable. A couple loads of gravel were brought into the back and spread out. These were needed to raise the pad for the driveway eventually anyway.

Next we had to reapply the plastic over the foundation floor. This was a repeat of our prior performance complicated by having to dry out several 25x100' sheets of plastic. We learned if you stretch then in the wind of an open field it is like the biggest kite in the world.

Once dried back out, we were were able to roll-out the airform and begin fitting it over the footing. This sounds much simpler than it is, and can be quite a workout for your shoulders and back.

Finally, the airform was attached to the foundation using metal strapping and Tapcon concrete screws. This was a fairly long process given the amount of perimeter Trinity Dome has. Part of this process included setting up the wooden contrictions around the saddle intersections between the domes.
[ add comment ] ( 1194 views ) | permalink


Archives



